Back to Adding Cost to a Project
The Task toolbar is located under the Task window and is used to add tasks to the selected pay item.
Selecting Add Task opens the window allowing you to enter the task description, quantity, units, and production. You change an existing task by selecting the Edit Task button on the main task screen.
Pressing the Save button will open the main Task window which displays the name, quantity, and production as well as the resources to accomplish the work. Press the cost type buttons to add/delete resources.
Continue to Subs, Suppliers, and Saving Tasks (WIP)