Reports > Project Images
Use the Project, Foreman, and Date picker dropdowns to select the data to be generated within the report. Note: There is an "Image Type" dropdown which will allow you to select the type of Images taken within the system.
From the "Top Right Corner" of the screen, click "Load Report" to generate the report.
Once the report is generated you'll be able to see the information and have the options to email the report from within the program itself or download it to your machine. You'll also be able to download the images directly.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article